The Wilson Inlet Catchment Committee Inc (WICC)

The Upper Hay Catchment Plan



Cover page
Summary
Introduction
Upper Hay Catchment
Background
Water assets
Land assets
Biodiversity assets
Cultural heritage
Purpose
Objectives
Primary MATS & RCTs
Plan development
Project management
Next steps
Research & Development
Stakeholders
Hydrology
Nutrients
Soil resource information
Perennial pasture
Engineering options
Biodiversity
Farm forestry
Monitoring
Action plan
Budget
Appendices
Bibliography


 

1.26 Budget

1.26.1 Proposed budget 06-07

TOTAL Budget for Upper Hay Catchment Plan Sept 06 - June 08

Items$ NAP/NHT$ Community
Operating
0.5 FTE level 2/4 Project Manager Dec 06-June 2008
Already funded to Dec 2006
60,000
Phase Perennials @ $60/ha for 150 ha9,00011,000
Permanent Perennials @ $60/ha for 3000 ha180,000210,000
Salt Tolerant Perennials @ $60/ha for 460 ha27,60032,000
Biodiversity Revegetation @ $450/ha for 50 ha22,50025,000
Riparian Revegetation @ $450/ha for 80 ha
To be funded thru WINRAP
36,00040,000
Farm-Forestry 125 ha @ $45056,25057,000
Surface Drainage 50 km @ $1,50075,000240,000
Remnant Vegetation Fencing @ $2,000/km for 100km200,000220,000
Waterways Fencing @ $2,000/km for 60km
To be funded thru WINRAP
120,000150,000
Stock Crossings @ $1,000/ crossings for 20 crossings20,00026,000
Alternate water points @ $1400 for 11 water points15,40015,000
Soil Testing (per kit) @ $200/kit for 55 kits11,00011,000
Soil Ameliorants (lime/gypsum/dolomite) @ $ 10/ha for 3,600ha36,00035,000
M & E Hydrology @ $15,000/subcatchments30,000
M & E Hydrology Landholder Participation @ $20/Time for 600 hrs x 1.8 yrs
21,600
R&D (pasture cuts and analysis)10,000
Communication/Publications8,000
Other funding212,250
Total funds required704,5001,122,000

Total investment for the Upper Hay strategic catchment

2,017,450

1.26.2 Proposed 1st Year Budget for on ground Implementation (Sept 2006-Jun 2007)

Items$ NAP/NHT$ Community
Operating
0.5 FTE level 2/4 Project Manager (6 months Dec 06-June 07)20,000
Phase Perennials @ $60/ha for 150 ha9,00011,000
Permanent Perennials @ $60/ha for 1,400 ha84,00096,000
Salt Tolerant Perennials @ $60/ha for 225 ha13,50016,000
Farm-Forestry 65 ha @ $45029,25028,000
Biodiversity Revegetation @ $450/ha for 30 ha13,50017,000
Riparian Revegetation @ $450/ha for 40 ha18,000 22,000
Surface Drainage 25km @ $1500/km37,500120,000
Remnant Vegetation Fencing @ $2,000/km for 40km80,00090,000
Waterways Fencing @ $2,000/km for 30km60,00075,000
Stock Crossings @ $1,000/ crossings for 10 crossings10,00013,000
Alternate water points @ $1400 for 8 water points11,20010,000
Soil Testing (per kit) @ $200/kit for 27 kits5,40010,000
Soil Ameliorants (lime/gypsum/dolomite) @ $ 10/ha for 1800ha18,00020,000
M & E Hydrology @ $15,000/subcatchment15,000
M & E Hydrology Landholder Participation @ $20/Time for 600 hrs
12,000
R&D (pasture cuts and analysis)5,000
Communication/Publications5,000
Other funding$107,250
Total required funding$327,100$540,000

1.26.3 Proposed 2nd Year Budget Implementation (07-08)

Items$ NAP/NHT$ Community
Operating
0.5 FTE level 2/4 Project Manager40,000
Phase Perennials @ $60/ha for 0 ha0
Permanent Perennials @ $60/ha for 1600 ha96,000114,000
Salt Tolerant Perennials @ $60/ha for 235 ha14,10016,000
Farm-Forestry 60 ha @ $45027,00026,000
Biodiversity Revegetation @ $450/ha for 20 ha9,00011,000
Riparian Revegetation @ $450/ha for 40 ha18,00022,000
Surface Drainage 25km @ $1,000/km37,500120,000
Remnant Vegetation Fencing @ $2,000/km for 60km120,000130,000
Waterways Fencing @ $2,000/km for 30km60,00075,000
Stock Crossings @ $1,000/ crossings for 10 crossings10,00013,000
Alternate water points @ $1400 for 3 water points4,2005,000
Soil Testing (per kit) @ $200/kit for 28 kits5,60010,000
Soil Ameliorants (lime/gypsum/dolomite) @ $ 10/ha for 1800ha18,00028,000
Clay Spreading @ $ 150/ha for 0ha0
M & E Hydrology @ $10,0005,000
M & E Hydrology Landholder Participation @ $20/Time for 600 hrs
12,000
R&D (pasture cuts and analysis)5,000
Communication/Publications3,000
Other funding105,000
Total368,200574,000

Review Proposed budget

$ NAP/NHT

$ Community
Other funds
2006-2007 1st year (10 months)$107,250
331,100540,000
2007-2008 2nd year (12 months)$105,000
377,400582,000
Total investment in Upper Hay catchment$212,250
704,5001,122,000